OPERATION
1540 02/12 Operation Section 4-9
© 2012 Alamo Group Inc.
OPERATION
Connecting the Rear Blade
1. Shorten or remove the tractor drawbar to avoid
interference when raising and lowering the rear
blade.
2. Board the tractor and start the engine. Position
the tractor to the blade with the 3-point lift arms
positioned between the respective set of blade
A-frame lift lugs. Note: Set the 3-point lift
control to “Position Control” so that the lift arms
maintain a constant height when attaching the
blade. See the tractor Operator’s Manual for
correct settings when attaching 3-point
equipment.
3. Turn off the tractor engine, set the parking
brake, place the tractor in park, and dismount.
4. One lift arm at a time, align arm end hole
between the set of holes of A-frame lift lugs.
Insert hitch pin through the lug and arm holes
and insert retaining pin into hitch pin. Walk
around to opposite side and repeat procedure
for remaining lift arm and hitch pin.
5. Extend or retract the 3-point top link to align its
end hole with the holes of the blade’s top link.
Insert the top link pin and retain with hairpin.
6. Adjust any lower link check chains, guide
blocks, or sway blocks to prevent the blade
from swaying side to side and possible contact
with tractor rear tires.
Never work under the Implement, the framework, or any lifted
component unless the Implement is securely supported or blocked up
to prevent sudden or inadvertent falling which could cause serious
injury or even death.
(SG-14)
7. PRE-OPERATION INSPECTION AND SERVICE
Before each use, a pre-operation inspection and service of the implement and tractor must be performed.
This includes routine maintenance and scheduled lubrication, inspecting that all safety devices are equipped
and functional, and performing needed repairs. DO NOT operate the unit if the pre-operation inspection
reveals any condition affecting safe operation. Perform repairs and replacement of damaged and missing
parts as soon as noticed. By performing a thorough pre-operation inspection and service, valuable down time
and repair cost can be avoided. OPS-U-0029